IMPORTANT CONSTRUCTION NOTICE: MAIN STREET CLOSURE FROM CHASE/MILFORD TO COURTHOUSE LANE BEGINS MAY 19

Beginning Monday, May 19, 2025, the Town of Bowling Green will begin an emergency sewer line replacement along Main Street as part of a critical infrastructure repair project.
🔧 Project Details:
• Scope: Sewer line replacement
• Construction Timeline: May 19 – June 30 (tentative, weather permitting)
• Safety: Construction zone will be marked off and closed to the public
• Road Closures: Full road closure on Main Street between Chase St./Milford St. and Courthouse Lane for the duration of the project
• Sidewalks Closures: Sidewalks are open during the duration of project; temporary closures may occur on an as-needed basis
Parking Lot Closures: Partial closures of Chase St. Municipal Parking Lot
Parking Alternatives
-
Business Parking - Parking for customers of Main Street businesses will be available in the designated business parking lots located behind the businesses on the east and west sides of Main Street.
-
Public Parking is available at Town Hall, located at 117 Butler Street, as well as on streets to the North and South of the project zone.
-
For more information on public parking, visit https://www.townofbowlinggreenva.gov/community/page/parking.
Detours- Follow all detour signage for alternate routes, please see additional detour information below
We understand this may cause inconvenience, and we appreciate your patience as we complete this vital work to repair our infrastructure. Please use alternate routes and follow posted detour signage.
Stay tuned to our Town Website and Facebook page for updates. Thank you for your continued support!